Ho Chi Minh City is accelerating four gateway build-operate-transfer (BOT) projects, with construction start dates set, as the city’s Department of Construction reports progress on key public-private partnership (PPP) initiatives. The Department has submitted a status report to the City People’s Committee, noting that the city is focusing on 14 PPP projects while fast-tracking the four gateway BOT projects.
The Highway 13 upgrade and expansion project, covering the section from the start of Binh Triệu Street to the border with Bình Dương Province, is financed under a BOT contract and includes two components.
Total investment is over 14,000 billion VND. The People’s Committee of Hiệp Bình Ward has issued land-recapture notices and approved detailed compensation, support, and resettlement plans for 1,041/1,041 cases.
Completion is expected in Q2 2026, while relocation of technical infrastructure is expected to be completed in December 2026.
Total investment is over 6,271 billion VND. The Finance Department is currently appraising the project’s pre-feasibility study.
The Highway 1 upgrade and expansion project was approved by the Ho Chi Minh City People’s Council in 2025 and includes three components.
Total investment is over 1,067 billion VND. Payments to affected households are ongoing, and site handover is expected from June 2026.
Total investment is 8,542 billion VND. Payments and site handover are anticipated between May and December 2026.
Prepared by the Department of Construction for BOT investment. The city is appraising the prefeasibility report from April 30 to May 5, 2026. The city plans to approve the project in Q4 2026, with construction completion expected by the end of 2028.
The Highway 22 upgrade and expansion project is also progressing with three components.
Compensation and resettlement, plus relocation of supporting infrastructure, with completion before August 30, 2026. Relocation of technical infrastructure is to be completed by December 30, 2026.
Relocation of infrastructure for the upgrade project in the 12th District area, with completion by December 2026.
BOT investment for the Highway 22 upgrade project (from the An Sương junction to Ring Road 3). Construction is scheduled to begin in January 2027 and be completed by December 2028.
The Bắc - Nam axis upgrade from Nguyễn Văn Linh to Bến Lức - Long Thành includes two components.
Compensation, support and resettlement, and relocation of technical infrastructure. Bidding for civil works is planned to commence in January 2027, with completion planned for December 2028.
BOT investment for the Bắc - Nam axis upgrade under a build-operate-transfer scheme. Construction is scheduled to start in January 2027 and finish by December 2028.

Premium gym chains are entering a “golden era” that is ending or already in decline, as rising operating costs collide with shifting consumer preferences toward more flexible, community-based ways to exercise. Long-term memberships are shrinking, margins are pressured by higher rents and facility expenses, and competition from smaller, more personalized…